BAC AWARDS MARCH 2019

  BAC AWARDS MARCH 2019      
Tender/ Contract No. Date Awarded Description Company awarded the contract Tender Amount
SPECIAL BAC - FRIDAY, 15 MARCH 2019    
8/2/43/2016-2017C SBAC, 15 March 2019 That an approval be granted to extend the appointment of Messrs BhekuAngel Trading & Projects, Contract No. 8/2/43/2016-2017C of R 5,803,737.94 to R6 964 485.53 incl. VAT with the scope increased by an amount of R1 160 747.59 incl. VAT for the upgrade of Scheme A&E to RDP standard and operate the borehole for an other additional four (4) months.  Messrs BhekuAngel Trading & Projects R 6 964 485,53
8/2/255/2013-2014D SBAC, 15 March 2019 Secondly, that an approval be granted to revise the appointment of Messrs Aurecon SA (Pty) Ltd, Contract 8/2/255/2013-2014D of R 1,950,241.94 Inclusive of VAT to R 2 242 778.23 Inclusive of VAT with the scope increased by an amount of R 292 536.29 Inclusive of VAT for the engineering services required for the upgrade of Scheme A & E to RDP standard of Crouch’s Bush Water Supply. Messrs Aurecon SA (Pty) Ltd R 2 242 778.23
SBAC, 15 March 2019 That the extension in [b] above be further extended by an amount of R2,170.360.47 Inclusive of VAT to R 4,916,986.67 Inclusive of VAT for the engineering services required for the upgrade of Scheme B, C & D to RDP standard and commission the whole Crouch’s Bush Water Supply Schemes. Messrs Aurecon SA (Pty) Ltd R 4,916,986.67
8/2/48/2018-2019D SBAC, 15 March 2019 It was resolved that Messrs Engineering Advice and Services be awarded Contract No. 8/2/48/2018-2019D for the Implementation and Management of the Rural Road Asset Management System in the Amathole District municipal area for a period of 36 months , for an amount of R 5 971 672.85 [Five million Nine hundred and seventy one thousand Six hundred and seventy two rands and eighty five cents] including 10% contingencies and 15% VAT.  Messrs Engineering Advice and Services R 5 971 672.85
8/2/49/2018-2019C SBAC, 15 March 2019 Supplier appointment:  That Messrs Izwelethu Cemforce cc be awarded the contract for the Supply and Delivery of Various Top Structures and Installation of Disabled and Low Flush Structures including Site Support for the ADM Sanitation Programme for 3 years Bid No. 8/2/49/2018-2019C for an amount of R 42 012.17 including 10% contingencies, 10% escalation and 15% VAT for a period of 36 months. Messrs Izwelethu Cemforce cc R 42 012.17 per unit
SPECIAL BAC - FRIDAY, 29 MARCH 2019  
8/2/12/2018-2019C SBAC, 29 March 2019 Contractor appointment:  That Messrs LG Construction cc be awarded the contract for the Gcuwa West Water Supply Scheme-Phase 3, Bid No. 8/2/12/2018-2019C at the tendered amount of R12 921 531.54 (Twelve million nine hundred and twenty one thousand five hundred and thirty one rands and fifty four cents) including 10% contingencies and 15% VAT for the duration of 12 months.  Messrs LG Construction cc R12 921 531.54
8/2/198/2012-2013(C) SBAC, 29 March 2019 Revision of appointment:  That Contract No. 8/2/198/2012-2013(C) for Messrs Kudec Engineering Development Services for the Provision of Consulting Engineering Services for the Upgrade of Hogsback Water Treatment Works project be revised from R1, 823,669.00 to R 4983 417.49 (VAT inclusive) with the scope increased by R 3,159,748.49 in order to cover phase 3 of the Hogsback Water Treatment Works. Messrs Kudec Engineering Development Services R 4 983 417,49
8/2/114/2015-2016D SBAC, 29 March 2019 Extension of contract:  That Contract No. 8/2/114/2015-2016D for the Bulk Water Supply to Ekuphumleni and 9 Villages Phase5 project previously awarded to Messrs Sosk Civil & Building Construction for an amount of R 14,495,781.26 inclusive of 10% Contingencies, and VAT, as tendered, be further extended by R 1 776 060.00 inclusive of VAT to cover additional work. Messrs Sosk Civil & Building Construction  R 1 776 060,00
 8/2/16/2009-2010D SBAC, 29 March 2019 Revision of appointment:  That the Contract 8/2/16/2009-2010D for the Provision of Consulting Engineering Services for Bulk Water Supply to Ekuphumleni and 9 Villages Phase 5 project previously awarded to Messrs Hatch Goba Consulting Engineers for an amount of R 2,612,203.13 inclusive of VAT, construction monitoring and disbursements, as tendered, be revised to R 4,996,444.12 with the scope increased by R 2,384,240.99 inclusive of Vat to covers additional work. Messrs Hatch Goba Consulting Engineers R 4,996,444.12
8/2/35/2018-2019C SBAC, 29 March 2019 It was resolved that Messrs Butheso Construction & Projects be awarded the contract for the Refurbishment of Lushington Bulk Water Supply: Tender No: 8/2/35/2018-2019C, for an amount of R6 423 104.23 [Six million Four hundred and twenty three thousand One hundred and four rands and twenty three cents] including 10% contingencies and 15% VAT for the period of 10 months.  Messrs Butheso Construction & Projects R 6 423 104,23
8/2/38/2018-20198C SBAC, 29 March 2019 Contractor appointment:  It was resolved that Messrs Butheso Construction & Projects be awarded the contract for the Stutterheim Water and Sewer Pipe Replacement Emergency Sewer Works Bid No : 8/2/38/2018-20198C, for an amount of R5 696 778.86 including 10% contingencies and 15% VAT for the period of six (6) months.  Messrs Butheso Construction & Projects R5 696 778.86 